SCHEDULE
Segment 1
Financial Project ID: 197534-2-32-01
Design of US 27 from north of I-4 to Barry Road
Phase I Plans: November 2008
Phase II Plans: April 2009
Phase III Plans: December 2009
Phase IV: April 2010
   
   
Segment 2
Financial Project ID: 197534-4-32-01
Design of US 27 from Barry Road to US 192
Phase I Plans: November 2008
Phase II Plans: April 2009
Phase III Plans: December 2009
Phase IV: April 2010
   
   
Financial Project ID: 424299-1-32-01
Design of the bridge over US 192
30% Structures Plan January 2009
60% Structures Plan July 2009
90% Structures Plan December 2009
100% Structures Plans April 2010
   
 
Project Status